Portland cement concrete slab-on-ground fabrication method for performance satisfaction and reduced carbon emission

Number of patents in Portfolio can not be more than 2000

United States of America

PATENT NO 11946211
SERIAL NO

18460883

Stats

ATTORNEY / AGENT: (SPONSORED)

Importance

Loading Importance Indicators... loading....

Abstract

See full text

A ground site for a building is prepared for construction of a portland cement concrete slab-on-grade (PCC SoG). Using a computerized weather application, weather conditions for a geographic locale that includes the ground site are monitored to identify a window-of-time during which the weather application indicates there is a less than 50% chance of precipitation at the geographic locale. The surface of the ground site is proof rolled during the window-of-time. Using concrete emplacement equipment during the window-of-time and only after the ground site passes proof rolling, wet concrete is emplaced on the ground site to a nominal thickness that does not exceed 7 inches and that is at least one inch less than a PCC SoG design for the ground site having a design thickness based on design guidelines set forth by the American Concrete Institute. Emplacing must be completed with at least 4 hours remaining in the window-of-time.

Loading the Abstract Image... loading....

First Claim

See full text

Family

Loading Family data... loading....

Patent Owner(s)

Patent OwnerAddress
AXIOM CARBON INDEX LLC11650 CANAL GRANDE DRIVE FT MYERS FL 33910

International Classification(s)

Inventor(s)

Inventor Name Address # of filed Patents Total Citations
Face,, III S Allen Sleepy Hollow, US 8 5
Van, Bergen Peter J Williamsburg, US 4 20

Cited Art Landscape

Load Citation

Patent Citation Ranking

Forward Cite Landscape

Load Citation

Maintenance Fees

Fee Large entity fee small entity fee micro entity fee due date
3.5 Year Payment $1600.00 $800.00 $400.00 Oct 2, 2027
7.5 Year Payment $3600.00 $1800.00 $900.00 Oct 2, 2031
11.5 Year Payment $7400.00 $3700.00 $1850.00 Oct 2, 2035
Fee Large entity fee small entity fee micro entity fee
Surcharge - 3.5 year - Late payment within 6 months $160.00 $80.00 $40.00
Surcharge - 7.5 year - Late payment within 6 months $160.00 $80.00 $40.00
Surcharge - 11.5 year - Late payment within 6 months $160.00 $80.00 $40.00
Surcharge after expiration - Late payment is unavoidable $700.00 $350.00 $175.00
Surcharge after expiration - Late payment is unintentional $1,640.00 $820.00 $410.00