Tower of a wind power plant and method for producing a tower of a wind power plant

Number of patents in Portfolio can not be more than 2000

United States of America Patent

PATENT NO 9091095
SERIAL NO

13704265

Stats

ATTORNEY / AGENT: (SPONSORED)

Importance

Loading Importance Indicators... loading....

Abstract

See full text

A method for the production of a tower of a wind power plant is disclosed wherein at least one tubular tower section is produced from annular precast concrete parts having two horizontal contact surfaces, which are arranged on top of one another. After casting, the annular precast concrete parts are set up in a processing station in the precast plant and the two horizontal contact surfaces of the precast concrete parts are processed in an orientation setting in a plane-parallel, material-removing manner. A tower of a wind power plant comprises at least one tubular tower section of annular precast concrete parts having two horizontal contact surfaces, which are arranged on top of one another. Both horizontal contact surfaces of the precast concrete parts are reworked in a plane-parallel, material-removing manner with a small parallelism deviation and a small flatness deviation.

Loading the Abstract Image... loading....

First Claim

See full text

Family

Loading Family data... loading....

Patent Owner(s)

Patent OwnerAddress
MAX BOGL BAUUNTERNEHMUNG GMBH & CO KGPOSTFACH 11 20 NEUMARKET 92301 GERMANY

International Classification(s)

Inventor(s)

Inventor Name Address # of filed Patents Total Citations
Bögl, Stefan Sengenthal, DE 11 56
Hierl, Martin Neumarkt, DE 3 42
Knitl, Josef Freystadt, DE 3 35

Cited Art Landscape

Load Citation

Patent Citation Ranking

Forward Cite Landscape

Load Citation

Maintenance Fees

Fee Large entity fee small entity fee micro entity fee due date
11.5 Year Payment $7400.00 $3700.00 $1850.00 Jan 28, 2027
Fee Large entity fee small entity fee micro entity fee
Surcharge - 11.5 year - Late payment within 6 months $160.00 $80.00 $40.00
Surcharge after expiration - Late payment is unavoidable $700.00 $350.00 $175.00